2025 GGS Roadmap

Q1

(January - March)

● Initial meeting with potential mining developer

● Start additional drilling (1,000 meters)

● Gold distribution analysis

● Begin laboratory tests (2,000 tests)

Q2

(April - June)

● Continue drilling (2,000 meters)

● Geophysics survey (10–13 km in two phases)

● Complete soil geochemistry measurements (500–1,000m)

● Conduct soil mechanics tests (200–300)

● Drone surface survey (10–15 km²)

● Continue laboratory tests (4,000 tests)

● Hydrogeological analysis of mining site and surroundings

Q3

(July - Sept)

● Continue drilling (2,000 meters)

● Continue laboratory tests (3,000 tests)

Q4

(October - December)

● Finalize drilling (2,000 meters)

● Complete remaining laboratory tests (1,000–2,000 tests)